Production building at Danish North Sea hubs
BlueNord expects maintenance work to finish shortly on the Dan and Gorm hubs in the Danish North Sea, the company said in an operations update.
The program included integrity inspection on the Dan complex and maintenance of the lift gas compressor on Gorm.
In addition, the Halfdan HCA gas-lift project in the same sector is close to completion. Operator TotalEnergies commissioned Semco Maritime to manage associated topside modifications on the Halfdan CA platform.
The program has involved hook-up of a gas-lift module, upgrading the design pressure of the liquid export pipeline, and support for pipeline cleaning and testing.
At the Tyra hub, production ramp-up continues. By the end of June, only two wells remained to be commissioned out of a total of 76 wells.
Highest production to date occurred on June 13, at 204.4 MMcf/d of gas and 36 MMboe/d of oil.