Santos

Santos is a global energy company with operations across Australia, Papua New Guinea, Timor-Leste and the US.

News

In addition, Santos reported that cleanup of the remaining three Barossa wells to the FPSO was completed during the first quarter.
April 24, 2026
Despite a temporary shutdown of the FPSO last month due to software issues, Santos expects the Barossa development in the Timor Sea to start commercial production operations in...
Oct. 16, 2025
Courtesy BW Offshore
BW Opal FPSO
Gas has begun flowing to the FPSO for the Santos-operated Barossa LNG project, with strong deliverability from five of the subsea wells tested to date.
Sept. 23, 2025
Courtesy INPEX
Bayu-Undan Project
Production from the Bayu-Undan gas condensate field in the Timor Sea has finally ceased, according to operator Santos.
July 17, 2025
Courtesy BW Offshore's Q1 2025 presentation
BW Opal FPSO.
The FPSO BW Opal has arrived at its offshore location at the Barossa gas field in the Timor Sea, which is about 285 km north of Darwin, Australia.
June 18, 2025
Courtesy Santos Ltd. LinkedIn
Barossa Gas Project
Santos has received a non-binding indicative proposal from a consortium led by XRG to acquire all its shares.
June 16, 2025
Santos has issued updates on two planned carbon capture and storage (CCS) projects offshore and onshore Australia.
April 17, 2025
Santos is sticking with its estimate of third-quarter 2025 for first gas from the Barossa LNG development in the Timor Sea offshore northwest Australia.
April 11, 2025
Courtesy Santos Ltd LinkedIn
Santos fourth-quarter 2024 report
Santos’ Barossa gas and condensate development in the Timor Sea was more than 88% complete at the end of last year, the company said in a trading update.
Jan. 24, 2025

Articles

Santos expects first gas from its Barossa project in the Timor Sea offshore northwest Australia in third-quarter 2025.
Aug. 22, 2024
Courtesy JERA
barossa
Santos’ Barossa gas project in the Timor Sea is currently 70.6% complete, the company said in an update.
April 18, 2024
Santos Energy says overall construction of its Barossa gas project in the Timor Sea is now at the 67% point, with first gas expected in third-quarter 2025.
Feb. 21, 2024
Photo 100153829 © wael alreweie | Dreamstime.com
australia
Santos and Carnarvon Energy are working to secure a rig for a next phase of drilling in the Bedout sub-basin offshore Western Australia.
Jan. 31, 2024
Courtesy Santos
barossa_gas_field
The Federal Court of Australia has ruled in favor of Santos in a court case brought by Munkara against Santos NA Barossa Pty.
Jan. 15, 2024
NOPSEMA, the Australian regulator, has accepted Santos’ Barossa development drilling and completions environment plan.
Dec. 18, 2023
Photo 98195845 © Anastasia Yakovleva | Dreamstime.com
Australia Court
The Federal Court of Australia has granted an interim injunction to prevent Santos initiating laying operations for the Barossa field development gas export pipeline in the Timor...
Nov. 2, 2023

Additional content from Santos

ID 8064538 © Brian Weed | Dreamstime.com
financing
Santos and its partners in the Darwin LNG joint venture have completed new syndicated bank loan facilities totaling $800 million.
Oct. 10, 2024
Courtesy TIMOR GAP
Bayu Undan
Santos and its partners in the Bayu-Undan upstream project in the Timor Sea have agreed to transfer a 16% interest to TIMOR GAP.
Sept. 6, 2024
Photo credit Tymunna Clements; Courtesy Environmental Defenders Office
Tiwi Elders seek Minister’s protection of cultural heritage from Santos pipeline.
Santos said that while it respects the cultural heritage of the Tiwi people and understands that there are a range of views about Barossa, it will defend the proceedings vigorously...
Oct. 31, 2023
Courtesy Santos
Upstream Gas Map
Santos and its partners have signed an MoU with TIMOR GAP to explore joint opportunities for the proposed Bayu-Undan CCS project in the Timor Sea.
Aug. 7, 2023
Gas and liquids production rose recently from the Bayu-Undan Field in the Timor Sea, due to increased plant uptime, Santos said in its latest results statement.
July 26, 2023
Photo 226123062 © Aju Arelt | Dreamstime.com
Timor Sea
Santos has signed four memoranda of understanding (MoUs) for the supply of emitted CO2 to the proposed Bayu-Undan CCS development offshore Timor-Leste in the Timor Sea.
May 3, 2023
Santos’ Barossa gas and condensate project in the Timor Sea, designed to backfill the Darwin LNG complex, is 56% complete.
April 20, 2023
Courtesy Santos
Santos
A group of Australian Indigenous people has lodged human rights grievances with a dozen banks urging them to withdraw a $1 billion loan to Santos Ltd. for its Barossa offshore...
April 5, 2023
Courtesy Santos full-year 2022 results report
Barossa FPSO construction
Santos’ Barossa gas project in the Timor Sea was recently 55% complete, the company said in its latest results statement.
Feb. 22, 2023
Santos has issued updates on its field expansion and development programs offshore Western Australia.
Jan. 19, 2023