Shell Chukchi drilling permit gets two amendments from US Interior

The US Interior Department has approved Royal Dutch Shell's applications to drill in the Chukchi Sea, but with a built-in stop concerning the availability of a capping stack.

Offshore staff

HOUSTON – The US Department of the Interior (DoI) has approved Royal Dutch Shell's applications to drill in the Chukchi Sea, but with a built-in stop concerning the availability of a capping stack.

TheDoI also said Shell could not drill both wells concurrently, but must P&A to top section of the first well before any drilling activity on the second.

Shell cannot drill into the reserves until a capping stack is posted for use, should it be needed. Then, Shell will have to submit a modified drillingplan to drilling into the target zone.

The initial capping stack aboard theFennica was damaged earlier this month. That vessel is to be repaired in Oregon.

7/23/15