Drilling begins off Varanus Is.
Harriet Joint Venture has begun its drilling program south of Varanus Island off Western Australia. The JV spudded the Simpson-4 discovery well in block TL/1 south of the island on July 31.
Simpson-4, the first of a five-well program, is a sidetrack from the existing Simpson-3H production well. The well is expected to take 14 days to reach its ptd of 2,257 meters. If all goes well, Simpson-4 will be the first of three deviated wells to be drilled from the Simpson Platform. The next well in the series will be South Simpson-1, which will target a separate closure further south. The final deviated well, South Tanami-1, will drill to a closure south of the Tanamio oil field. If the wells are successful, they will all be completed and brought into production immediately. A fourth exploration well, Tirari-1, will target a separate closure south of the South Tanami closure. The final well in the series, Endymion-1, will be drilled from the Sinbad Platform. Apache Corp. is operator of the joint venture.