North Sea Hejre jacket loaded out

Heerema Fabrication Group has skidded the 8,500-ton launch jacket for DONG Energy’s Hejre field platform onto a barge at the quayside in Vlissingen.

Apr 23rd, 2014
Hejre oil and gas field platform jacket
Hejre oil and gas field platform jacket

Offshore staff

VLISSINGEN, the NetherlandsHeerema Fabrication Group has skidded the 8,500-ton launch jacket for DONG Energy’s Hejre field platform onto a barge at the quayside in Vlissingen.

Technip commissioned the eight-leg jacket, which measures 60 x 35 x 85 m (197 x 115 x 279 ft). The 900-ton pre-drilling wellhead deck is expected to be loaded out in the first week of May, and will then sail to theHejre location in Danish North Sea for installation.