Petrofac to supply substations for Seagreen wind farm offshore Scotland

Jan. 16, 2020
Petrofac has entered into a preferred supplier agreement with SSE Renewables to design, supply, and install the HVAC onshore and offshore substations for the Seagreen wind farm project in Scotland.

Offshore staff

LONDON Petrofac has entered into a preferred supplier agreement with SSE Renewables to design, supply, and install the HVAC onshore and offshore substations for the Seagreen wind farm project in Scotland.

Located 27 km (17 mi) off the coast of Angus, once constructed it will be the country’s largest wind farm.

Petrofac has started early work on the project. Subject to a final investment decision expected in the coming months, its full scope will include, on a lump-sum basis, the engineering, procurement, fabrication, transportation, installation, and commissioning of the offshore substation platform, including the topsides, jacket and piles.

The onshore substation EPC scope includes all civil work and major equipment.

01/16/2020