Subsea7 wins Tiberius project installation contract

Contractor to fabricate, transport and install SCR, flowline and umbilical for Kosmos Energy.

Subsea7 says that it has won what it describes as a “sizeable contract” from Kosmos Energy Gulf of Mexico Operations for the Tiberius project in the deepwater US Gulf.

The development is located in lease KC-964 at a water depth of approximately 2,200 meters (about 7,220 feet).

The scope covers the fabrication, transportation and installation of a 14-kilometre steel catenary riser (SCR) and wet-insulated flowline to the Lucius spar, plus installation of an umbilical and subsea controls.

Project management and engineering will begin in the coming months at Subsea7’s Houston office, with offshore activities expected to start in 2028.

Subsea7 defines a “sizeable contract” as being between $50 million and $150 million.

Background on Tiberius: 

  • Discovery: Kosmos Energy announced the oil discovery in October 2023 at the Tiberius exploration well in Keathley Canyon Block 964. The well tested a four-way structural trap in the outboard Wilcox trend and encountered ~250 ft (~75 m) of net oil pay in the primary target. It was drilled in roughly 2,300 m (7,500 ft) of water to a total vertical depth of about 7,800 m and was cased as a potential future producer.
  • Location and development concept: About 6–10 km southeast of the existing Occidental-operated Lucius spar. The project is being developed as a subsea tieback to that facility. Partners reached FID on Phase 1A in 2026 (around March); it involves completing the already-drilled well. First oil is targeted for the second half / end of Q3 2028. Initial rates are indicated around 13,000 b/d oil, with potential later phases reaching up to ~30,000 b/d oil and 9 MMscfd gas.
  • Ownership: Kosmos (operator) 33.34%, Occidental 33.33%, Navitas Petroleum US 33.33%. Navitas acquired its interest from Kosmos and Occidental earlier in 2026.
  • Lucius spar: A key deepwater host in the area (originally Anadarko, now Occidental). It already handles production from other fields such as Buckskin, making the short tieback economically attractive.

This is a classic infrastructure-led development: a relatively modest discovery near existing processing capacity, which explains the short timeline from 2023 discovery to 2026 FID and 2028 first oil. The Subsea7 contract covers the critical subsea pipeline and controls package that enables the tieback.

 

About the Author

Bruce Beaubouef

Bruce Beaubouef

Senior Lead Reporter / Managing Editor

Bruce Beaubouef is Managing Editor for Offshore magazine. In that capacity, he plans and oversees content for the magazine; writes features on technologies and trends for the magazine; writes news updates for the website; creates and moderates topical webinars; and creates videos that focus on offshore oil and gas and renewable energies. Beaubouef has been in the oil and gas trade media for 25 years, starting out as Editor of Hart’s Pipeline Digest in 1998. From there, he went on to serve as Associate Editor for Pipe Line and Gas Industry for Gulf Publishing for four years before rejoining Hart Publications as Editor of PipeLine and Gas Technology in 2003. He joined Offshore magazine as Managing Editor in 2010, at that time owned by PennWell Corp. Beaubouef earned his Ph.D. at the University of Houston in 1997, and his dissertation was published in book form by Texas A&M University Press in September 2007 as The Strategic Petroleum Reserve: U.S. Energy Security and Oil Politics, 1975-2005.

Sign up for our eNewsletters
Get the latest news and updates
Subsea Tieback Forum & Exhibition
SAVE THE DATE
Subsea Tieback Forum & Exhibition
February 16 - 18, 2027
Henry B. Gonzalez Convention Center, San Antonio, TX