Valeura Energy progressing production-boosting campaigns at two fields offshore Thailand

A new drilling campaign on the Nong Yao field in offshore Block G11/48 should finish during Q4.
July 8, 2025

Valeura Energy has issued updates on two of its current field development projects in the Gulf of Thailand.

A new drilling campaign on the Nong Yao field in offshore Block G11/48 should finish during Q4. It involves drilling around development wells in total from the three existing Nong Yao wellhead facilities, including the first infill on the Nong Yao C platform which was installed last year.

In May, Valeura took FID on redeveloping the Wassana field in license G10/48 through the addition of a new central processing platform.

This should increase production, cut costs, and form a tie-in hub for future satellite wellhead platforms. The project is moving into the construction phase, with first production targeted for Q2 2027.