From decommissioning to expansion, Woodside shares offshore oil and gas initiatives

Woodside is actively decommissioning older offshore assets, addressing safety issues and planning platform removals, while also progressing new exploration and development projects.
Aug. 19, 2025
3 min read

Key Highlights

  • Construction has now started on nearly all the major components of the Trion oilfield project offshore Mexico, aside from the FSO.
  • In the US sector, bp and Woodside have sanctioned new water injection wells at the Atlantis Field, while infill drilling continues at Mad Dog. 
  • Decommissioning efforts in Australia include the safe removal of wells and platforms, with safety concerns influencing project costs and timelines.
  • The company continues exploration and development activities in Trinidad, with the Calypso project and other gas discoveries under study.

In 2025, Woodside is progressing on key offshore projects with detailed design, construction and engineering activities, while addressing operational and safety challenges, aiming for increased production capacity and strategic growth in global offshore oil and gas, according to its first-half 2025 results statement released on Aug. 19.

Gulf of Mexico

Woodside Energy says the deepwater Trion Field development in the Gulf of Mexico has passed the 35% completion point.

Trion, 180 km from the Mexican coast and 30 km south of the US/Mexico maritime border, will produce via 24 subsea wells to a semisubmersible FPU with a production capacity of 100,000 bbl/d of oil, offloading to an FSO.

Woodside says it is targeting first oil in 2028.

During the first half, the detailed design of the FPU was finalized, with construction of three topside modules and the living quarters progressing, and fabrication completed of the platform’s turbo machinery and equipment. 

Construction of the FSO, to be provided by SBM Offshore, is due to start later this year, while fabrication is underway for the disconnectable turret mooring as well as the FSO and FPU anchor piles.

All subsea equipment, trees and topside control systems have been ordered and all main contracts now awarded, including those for drilling and completion services, the gas pipeline installation, FSO operating and maintenance, and support vessels.

Since March, all project costs have been split 60% by Woodside (operator) and 40% by PEMEX (sole project partner).

In the US Gulf, the bp-led partnership has taken FID on the Atlantis Major Facility Expansion project, which calls for two new water injector wells and upgrades to the semisubmersible platform’s topsides water injection system to raise water injection capacity.

The partners (Woodside, 44%) are aiming for first water injection from the new facilities in 2027.

Another of the company’s ventures in US waters is the Mad Dog oil and gas field development, which produces through the offshore A-Spar and the Argos platform. The latter was installed for Mad Dog Phase 2, an ongoing development of the field’s southern flank.

Infill drilling and completion activity continued throughout first-half 2025 to support both production facilities, with the Mad Dog Southwest Extension recently brought online, delivering first oil 25 months post-completion of the appraisal well.

Offshore Trinidad

Concept select engineering and subsurface studies continue for the Calypso project in 2,100 m water depth, 220 km offshore Trinidad. Calypso comprises various gas discoveries in Block 23(a) and Block TTDAA 14, and it is close to existing infrastructure.

Offshore Australia

Offshore Western Australia, the retrieval of the decommissioned Echo Yodel umbilical should get underway later this year.

Woodside continues to review decommissioning workscopes for the Minerva, Stybarrow and Griffin fields. It has identified potential safety issues with the as-left condition on some closed sites that could impact execution, and those challenges were the main cause of a $445-million pre-tax ($218 million post-tax) restoration expense being recognized in the company’s profit and loss results.

At Bass Strait offshore southeast Australia, however, the Gippsland Basin joint venture (ExxonMobil and Woodside) has safely completed P&A so far of more than 200 wells, including the Bream B and Kingfish A platform wells earlier this year.

Detailed engineering and execution planning continues for the planned Bass Strait offshore platform removal campaign in 2027.

Learn more about Woodside's first-half 2025 production numbers:

About the Author

Jeremy Beckman

Editor, Europe

Jeremy Beckman has been Editor Europe, Offshore since 1992. Prior to joining Offshore he was a freelance journalist for eight years, working for a variety of electronics, computing and scientific journals in the UK. He regularly writes news columns on trends and events both in the NW Europe offshore region and globally. He also writes features on developments and technology in exploration and production.

Sign up for Offshore eNewsletters