P.2 ~ Red Hawk stands as first spar ever decommissioned in GoM

April 9, 2015

Displaying 2/2 Page 1, 2
View Article as Single page

"Actually, one of the things that most excited the Louisiana Wildlife and Fisheries team about the spar becoming an artificial reef was because of the soft, sandy bottom of the Gulf of Mexico. It doesn't have a lot of cavernous, hard surfaces for marine ecosystems to develop on," he said. "The spar would be able to create a really unique habitat in the Gulf of Mexico, something that they can study in the future and see what kind of positive impacts it has, and how that will impact the future projects."

Anadarko and its contractors began to mobilize, including InterMoor, the project's main contractor, whose scope of work included engineering, offshore work, decommissioning, towing, ballasting and deballasting, mooring disconnect/recovery, and reefing.

TheVB 10,000 removes the Red Hawk cell spar's topsides. (Photo courtesy InterMoor)

The decommissioning work would take place during a 24-day period in the heart of hurricane season, between August and September 2014. Kavanagh said that planning for a decommissioning was more than just considering the project simply the opposite of a commissioning.

"It's different mentally and emotionally to have something one day and know that the next day it's gone; you won't have it anymore," he said.

Versabar's VB 10,000, a fully-automated DP-3 barge-mounted dual truss system, was used for the removal of the 3,800-ton (3,447 metric ton) topsides. The company says it is the largest lift vessel to be built in the US, with a hook height of 178 ft (54 m) and a lift capacity of 7,500 tons (6,803 metric tons). Versabar says that it was the first time the VB 10,000 had performed a lift on a floating facility. The topsides were floated, which meant that there were two independent floating structures, something else that required much planning and engineering.

Todd Veselis, general manager, Permanent Moorings for InterMoor, said that because the topsides were removed completely, workers had to ballast the hull down exceptionally low – down to around 15-20 ft (4-6 m) of freeboard, he said– so that the VB 10,000 could completely lift the topsides off and to transport them for recycling.

Additionally, the entire operation had to be storm-safe. Nobody could wait for perfect weather in the hurricane-prone GoM to perform any part of the decommissioning. For example, deck legs, which took one day each to cut through, were pre-cut and then re-attached with a temporary clip, albeit one strong enough for a 10-year GoM hurricane, Kavanagh said, noting that the company worked with agencies including the Coast Guard and other agencies to ensure that these implements were necessarily robust.

Decommissioning the Red Hawk spar, with its unique air-over-water ballasting system, would represent InterMoor's first time to work in ballasting and deballasting.

"We had to engineer a separate, remote ballasting system to be able to facilitate the topside lift," Veselis explained. "Then, once the topsides were gone, we had to deballast the hull so that we could finish the mooring disconnect; then eventually tow to the reefing site; set it on bottom; and then do the actual reefing."

Deballasting following topsides removal. (Photo courtesy Anadarko)

Of course, InterMoor also had to plan for the spar's rapidly-diminishing parts and pieces. With the mooring system running from the topsides, much engineered preparation was necessary prior to the lift. The six-point mooring system led to one work chain. InterMoor cut the work chain into three sections and attached these to the mooring chains on one side of the hull. The mooring lines were then slacked three to one side prior to topsides removal.

That alleviated tension for the entire system, Veselis explained. It also allowed for topsides removal and formed as the basis for the removal of the mooring.

After VB 10,000 removed the topsides, another vessel was called in to assist with removing the spar: McDermott's Derrick Barge 50, a DP-2 heavy-lift and lowering vessel. Veselis said it acted as a staging area throughout the operation, in addition to ballasting, towing, reefing and mooring disconnect, accommodation, and support services.

The spar hull was ballasted back up, and DB 50 removed the spar hull, with Kirt Chouest remaining behind for mooring recovery.

Veselis saw the Red Hawk spar as a lifetime project: InterMoor, as a predecessor company, was involved with the installation, and he was a project engineer on the original installation. That information, along with the companies' pre-existing relationship, helped operations run smoothly.

Kavanagh said that during the peak of decommissioning, there were more than 300 workers offshore spread out across multiple vessels.

"With a few minor exceptions, including weather delays, the operation ran smoothly, which is credited to a comprehensive planning phase," he explained. "A great deal of practical experience was gained through the decommissioning of Red Hawk that will be applied to future projects both for Anadarko and the industry."