Grenland gets FMC LOI for Troll subsea structure

Grenland Group has signed a letter of intent with FMC Technologies to fabricate, assemble and test a six-slot manifold and integrated template for Norsk Hydro's Troll O2 project.

Offshore staff

PORSGRUNN, Norway --Grenland Group has signed a letter of intent with FMC Technologies to fabricate, assemble and test a six-slot manifold and integrated template for Norsk Hydro's Troll O2 project.

Delivery of the NOK35 million ($5.8 million) 350 metric ton (386 ton) subsea structure is scheduled for Jan. 12, 2008.

The Vega and Vega South gas and condensate fields are in 380 m (1,247 ft) of water in blocks 35/8 and 35/11 about 80 km (50 mi) west of Florø in Sogn and Fjordane.

5/10/007