Offshore staff
BLYTH — Harlyn Solutions, a UK-based transporting company, has completed Phase 1 of the offshore substation transport for the Moray West offshore wind farm.
The two substations have arrived in the Cromarty Firth to await their installation at the wind farm.
Harlyn Solutions has delivered the required engineering, vessels and marine support to perform the complex turnkey operations in addition to the upcoming offshore sea fastening release prior to transfer to installation vessel and then installation on their monopiles.
Pete Geddes, Moray West project director, said, “As the Moray West project progresses through installation, we are delighted that Harlyn Solutions has safely delivered the two topsides to the Port of Nigg, ready for the final journey to the wind farm site."
The substations will shortly be loaded out to the installation vessel prior to the offshore installation and hookup.
11.14.2023