Noble commissions process module for Leviathan platform offshore Israel

Feb. 22, 2018
Noble Energy has contracted Schlumberger to engineer and supply a 2,000-ton single-lift process module for installation on the Leviathan production platform in the Eastern Mediterranean.

Offshore staff

HOUSTONNoble Energy has contracted Schlumberger to engineer and supply a 2,000-ton single-lift process module for installation on the Leviathan production platform in the Eastern Mediterranean.

The scope of the contract includes pretreatment, salt removal and regeneration of monoethylene glycol (MEG) for reinjection in the subsea flowlines for hydrate inhibition. Schlumberger will supply its PUREMEG reclamation and regeneration system.

Project management, engineering, fabrication, installation support, and life of field activities will be managed by a globally integrated team.

Mohamed Kermoud, president, OneSurface, Schlumberger, said: “Our advances in MEG technology combined with our global execution strategy have placed us in a position to deliver to Noble Energy an integrated, optimized and capital-efficient solution.

“Schlumberger has taken a proactive approach, collaborating with Noble and their suppliers on the project, to help ensure that Noble Energy’s project vision and goals are realized.”

This follows the contract award to OneSubsea, a Schlumberger company, by Noble Energy for the supply of 10,000-psi horizontal production trees, tree-mounted controls, off-tree controls and topsides controls for the same project.

02/22/2018