Breagh gas platform in place in North Sea

The heavy-lift vessel Thialf has completed installation of the Breagh Alpha platform in the UK North Sea for RWE Dea UK.

Pennwell web 500 354

Offshore staff

TEESSIDE, UK – The heavy-lift vessel Thialf has completed installation of the Breagh Alpha platform in the UK North Sea for RWE Dea UK.

The 4,000-metric ton (4,409-ton) jacket and eight piles were installed in 62 m (203 ft) of water, 100 km (62 mi) off Teesside, northeast England.

This was followed by lifting and setting of the 1,400-metric ton (1,543-ton) integrated deck topsides.

Earlier this year installation was completed of the pipelines that will transport gas from the Breagh field to the shore. First gas is scheduled for mid-2012. Breagh is in blocks 42/12a and 42/13a. The field is being developed in two phases.

Phase 1 entails gas export the 20-in. (51-cm) pipeline from the Breagh Alpha platform to Coatham Sands, Redcar, and onward through a 10-km (6.2-mi) overland pipeline to the Teesside Gas Processing Plant (TGPP) at Seal Sands.

Phase 2 – field development approval is expected early next year – will likely involve additional wells in the east of the field drilled from another platform (Breagh Bravo) tied back to Alpha.

Pennwell web 500 354
Topside platform during installation by Thialf.

10/24/2011

More in Field Development