Ichthys project reaches peak construction activity

Oct. 17, 2014
Australia's Ichthys project is now officially half way to completion. Three mega-projects in one, the Ichthys project will involve some of the largest offshore facilities in the industry, significant onshore infrastructure, and an 889-km (552-mi) pipeline connecting the two. When complete, the pipeline will become the fifth-longest subsea pipeline in the world.

Wendy Laursen
Contributing Editor

Australia's Ichthys project is now officially half way to completion. Three mega-projects in one, the Ichthys project will involve some of the largest offshore facilities in the industry, significant onshore infrastructure, and an 889-km (552-mi) pipeline connecting the two. When complete, the pipeline will become the fifth-longest subsea pipeline in the world.

To date, all 889 km (552 mi) of the 42-in. pipeline has been produced and coated, and pipeline construction started mid-year. The Saipem pipelay vesselSemac-1 is installing around 120 km (74.5 mi) of pipe through Darwin Harbour and beyond before transferring it to a deepwater lay barge, Saipem's Castorone, which will take it all the way to the Ichthys field.

Throughout the year, 30,000 metric tons (33,069 tons) of equipment and 400 km (249 mi) of flexible and rigid lines will be installed on the seabed to gather and distribute the process fluids to the wells and the production liquids from them. Subsea structure fabrication and rigid pipeline assembly is well advanced in McDermott's and Heerema's yards in Batam. Flexible riser production is also in progress at various locations in Europe including the 110-m (360-ft) high, 7,000-metric ton (7,716-ton) riser support structure that will be installed by Heerema's deepwater construction vesselAegir.

The production drilling rigEnsco5006 is undergoing 175 days of extensive upgrades before being towed to the field to commence drilling the first production wells in October 2014. By 4Q 2014, the first topsides will be lifted on to the central processing platform (CPF) and FPSO hull, paving the way for modules integration and then commissioning.

The Ichthys reservoirs are located in the Timor Sea around 200 km (124 mi) off the Western Australian coast, and are projected to be the largest discovery of hydrocarbon liquids in Australia in more than 40 years. (All photos/images courtesy INPEX except where noted)

Project scope

The Ichthys reservoirs are located in the Timor Sea around 200 km (124 mi) off the Western Australian coast, more than 800 km (497 mi) southwest of Darwin. There are two geological horizons with a total of around 12 tcf of gas and 500 MMbbl of condensate. This makes it the largest discovery of hydrocarbon liquids inAustralia in more than 40 years.

Once in production, most condensate will be transferred from the CPF to the nearby FPSO for offshore processing. The remainder will be sent to Darwin with the gas via the pipeline.

The huge FPSO – one of the largest and most sophisticated to be deployed worldwide – will be positioned about 3 km from the CPF to treat and export the condensate. The 336 m by 59 m (1,102 ft by 193.5 ft) hull has now been launched from the dry dock at the Daewoo Shipbuilding and Marine Engineering shipyard in Okpo, South Korea. Designed with a storage capacity of nearly 1.2 MMbbl, the FPSO will be a weather-vaning ship-shaped vessel that will be permanently moored on a non-disconnectable turret. The turret is one of the most complex pieces of equipment used on the project.

TheIchthys FPSO will be positioned about 3 km from the central processing facility to treat and export the condensate.

Major contractors

Some of the world's best known contractors are engaged for the project:

  • The CPF is being built by Samsung Heavy Industry, with Mustang as the detailed engineering subcontractor
  • The FPSO is being built by DSME, with Technip as the detailed engineering contractor
  • All rotating equipment contracts have been awarded to GE in Italy (Nuovo Pignone) and France (Thermodyne)
  • The FPSO turret is being built by SBM
  • The subsea production system is being supplied by Vetco, part of GE group
  • The umbilical, risers and flow lines EPCI contract has been awarded to McDermott. The installation has been subcontracted to Heerema
  • The gas export pipeline contract has been awarded to Saipem with the shallow water part subcontracted to Semac and Boskalis for the dredging and rock dumping
  • 60% of the pipe will be supplied by Mitsui with Europipe in Germany. Nippon Steel and Sumitomo will supply 20% each. External coating, including concrete coating, and internal flow coating is the responsibility of Mitsui/ Bredero Shaw.
The Ichthys field will include an offshore central processing facility; a floating production, storage, and offloading (FPSO) facility; tankers; and an 889-km (552-mi) subsea pipeline to move the gas to market.

Pipeline challenges

The 42-in. pipeline has taken a total of one and a half years to manufacture. It has 75,000 joints, 690,000 metric tons (76,059 tons) of steel and will weigh 1.2 mega-tonnes (1.322 MM tons) including the concrete coating. It will take a year to install with over 600 people working on the pipelay barge.

Jarrad Blinco is leading the pipeline team at INPEX: "We decided on using three mills to provide supply chain redundancy and schedule flexibility," he said. "We had 100% of their capacity for quite some time, but we sequenced the work to provide a steady, continuous supply of pipe to the coating yards."

The pipeline coating process starts with an internal flow coat application to enhance the flow performance characteristics of the gas stream, followed by an external anti-corrosion asphalt enamel coating. It is then coated externally with concrete of varying thicknesses to provide additional weight which helps pipeline dynamic stability on the seabed.

"Because it's such a long pipeline, the seabed is highly variable," Blinco commented. "The pipeline traverses sand, clays, silt and rocky outcrops, but one unexpected element was on the approach to the field, where we discovered a big escarpment about 30 m (98 ft) high. So today, if you look at the pipeline route you can see there's a big dogleg as we avoid this geohazard."