Acergy reports progress on new office campus
Offshore staff
ABERDEEN, UK -- Construction of Acergy's new office campus in Westhill, Aberdeenshire is on schedule for completion March 2008.
Construction began in Dec. 2006. Eight months into the development – all structural steelwork on the 17-acre office complex has been completed. Approximately 50% of the wall cladding is finished, while work to secure the building against wind and water is on schedule to be completed by late summer 2007.
The workshop and warehouse building is being constructed in two phases with the steelwork, cladding, and structural floors nearing completion to the east wing. Structural steelwork to the west wing is now 50% complete.
8/1/2007