Oil flows from Clair

The BP-operated Clair field, 47 mi west of Shetland began oil production Feb. 25. Initial production is through the original appraisal well, which has now been brought online. Planned production will plateau at 60,000 b/d through a continuous platform drilling program.

The BP-operated Clair field, 47 mi west of Shetland began oil production Feb. 25. Initial production is through the original appraisal well, which has now been brought online. Planned production will plateau at 60,000 b/d through a continuous platform drilling program.

The Clair development comprises a conventional platform with production and process topsides facilities supported by a fixed steel jacket. The development is the first steel based structure in the west of Shetland area.

Oil from the field will be exported to the Sullom Voe Terminal in Shetland via a 105 km, 22-in. diameter pipeline. Gas will be exported through a 10 km, 6-in. diameter spur line into the Magnus Enhanced Oil Recovery trunkline.

"This has been a long journey – 27 years since Clair was discovered – but through advances in technology, a pioneering approach to project engineering and fabrication, and the perseverance of the Clair partnership, we have managed to bring Clair to fruition," Dave Blackwood, director and business unit leader for BP's North Sea business, says.

BP operates the Clair field with 28.6% interest. Partners include ConocoPhillips with 24% interest, ChevronTexaco with 19.4% interest, Shell with 18.7% interest, and Amerada Hess with 9.3% interest.

2/25/05