StatoilHydro tests first full-scale subsea compression train - Offshore
| RssImageAltText

StatoilHydro tests first full-scale subsea compression train


Published: Apr 21, 2008

Offshore staff

STAVANGER, Norway -- StatoilHydro has completed the first-ever full-scale test of subsea compression at its Kårstø Laboratory in western Norway.

Two compressor prototypes ? a MAN Turbo and Siemens unit ? will be tested at K-lab over a two-year period. The MAN Turbo unit was installed this past winter and the Siemens compressor will be ready for trials in 2009.

"This is a unique technology testing endeavor crucial for assessing subsea compression as a possible solution for offshore fields like Åsgard and Mikkel," says Rolv Herfjord, StatoilHydro Åsgard Minimum Flow Project manager. "If the testing is successful, we can assess using subsea installations instead of offshore platforms."

04/21/2008

Offshore Videos

More Offshore Videos


Current issue
Volume 70, Issue 3
March 2010
1003off-cover.jpg
Maps, Posters & Surveys

Maps & Posters
Surveys
Surveys in Excel



Offshore Magazine Article Categories:

Regional Reports Geology & Geophysics
Oil Drilling and Completion Oil and Gas Pipelines & Transportation
Oilfield Development and Construction Oil Production
Subsea Oil Rigs & Vessels
Oil Equipment & EngineeringOffshore Magazine Current Issue
Business BriefsArchives