Operators planning some 5,800 mi of offshore pipelines through 2017

Bruce Beaubouef
Managing Editor

Operators and developers are studying, planning, and building more than 5,800 mi of oil and gas pipelines to bring these supplies from offshore fields to onshore markets.

Europe is the clear leader in offshore pipeline projects, with more than 2,500 mi of systems being built and planned. The largest project being planned offshore Europe is the proposed South Stream pipeline. It would move Russian gas through the Black Sea to Bulgaria through a 560-mi, 32-in. pipeline to be installed in waters down to more than 7,300 ft. Gazprom and Eni, the developers of South Stream project, announced earlier this year that they will make a final investment decision in November and start construction in December.

The Middle East is the next most active region, with nearly 1,100 mi of oil and gas pipelines being built and planned. The most notable project in this region – and a big contributor to the region's total – is the proposed South Asia Gas Enterprise (SAGE) pipeline project, which proposes to move natural gas from the Oman Middle East Compression Station (MECS) to Gujarat, India, by building 807 mi of 24 to 27-in. pipe through the Arabian Sea, in waters down to 11,100 ft. The project is currently under study, and project developers are looking at a 2017 in-service date.

The South Pacific is another active region for offshore pipeline activity, with Chevron's Gorgon and Wheatstone projects both having associated pipeline systems as part of the development projects. Work is currently underway on the 43-mi, 20-in. Gorgon gas trunkline, with installation contractor Clough working to complete the line before the end of the year. The biggest offshore pipeline project in this region is associated with the Ichthys project offshore Western Australia. It calls for 552 mi of 42-in. pipe to move gas from an offshore processing facility to Darwin, Australia. An installation contract has been awarded to Saipem, who will work toward a 2014 completion date.

In the Gulf of Mexico, Williams and DCP Midstream Partners are pushing forward with plans to extend the Discovery natural gas gathering pipeline system. The Keathley Canyon Connector involves the construction of a 215-mi, 20-in. pipeline. It will gather production from the Keathley Canyon, Walker Ridge, and Green Canyon areas in the central deepwater Gulf. Construction is expected to begin next year, and work toward a mid-2014 in-service date.

Also in the Gulf, Enterprise Products Partners and Genesis Energy are developing plans for a new crude oil gathering pipeline serving the Lucius development area. The 149-mi, 18-in. SEKCO oil pipeline is would connect the Lucius truss spar floating production platform to an existing junction platform at South Marsh Island 205. There, it would connect to the Enterprise-operated Poseidon pipeline system. The SEKCO oil pipeline is expected to begin service by mid-2014.

Offshore South America, Petrobras is also moving forward with plans to move gas from the Guara and Lula Northeast FPSOs in its Lula field to other systems that will take the gas to onshore markets.

The inaugural Global Offshore Pipeline Construction Survey – a detailed project-by-project listing of all the major, large-diameter offshore oil and gas pipeline systems being built, planned and studied – makes its debut below.

Click here to view Global offshore pipeline construction survey

Related Articles

Pipeline issues stall production from Huntington in North Sea

Nov 7, 2014

Production from the Huntington field in the UK central North Sea has had to be shut in temporarily, according to partner Noreco.

North Sea Alvheim partners set to sanction more tiebacks

Nov 5, 2014

Lundin Petroleum has issued a progress report on its various development projects in the Norwegian North Sea.

UAE/India group to revamp Mumbai High North

Nov 3, 2014 ONGC has awarded a consortium of Valentine Maritime and Indian contractor Supreme Offshore Construction & Technical Services a $215-million contract for the MHNRD Phase III pipeline project for...

Forties oil pipeline secured ahead of subsea engineering work

Oct 31, 2014

STATS Group has completed an isolation program for Apache on the Forties pipeline system (FPS) in the UK central North Sea.

Unique Wellube to supply ADMA-OPCO with seal plugs

Oct 29, 2014 Abu Dhabi Marine Operating Co. (ADMA-OPCO) has contracted Unique Wellube, a division of Unique Maritime Group, for the supply and engineering of mechanical seal plugs for a significant pipeline iso...

Trending News

ExxonMobil awards Alternate Path completion license to Delta Screens

Nov 21, 2014

ExxonMobil Upstream Research Co. has awarded Delta Screens & Filtration LLC a limited international license to ExxonMobil’s Alternate Path technology patent portfolio for gravel packing cased-hole and openhole completion wells.

 

EMGS receives survey contract award in Brazil

Nov 21, 2014

Electromagnetic Geoservices ASA has received a contract worth $1.5 million for a research project in Brazil.

QinetiQ acquires seismic capabilities from SR2020

Nov 21, 2014

QinetiQ has acquired the seismic processing and imaging capability of SR2020 Inc. for a purchase price of up to $1.7 million.

Ocean Installer to place Delta House umbilicals

Nov 21, 2014

Ocean Installer has been awarded a contract for an umbilical installation project with Oceaneering for LLOG Exploration on the Delta House project.

Petrobras starts-up FPSO Cidade de Ilhabela

Nov 21, 2014

Petrobras has started production through the FPSO Cidade de Ilhabela from the Sapinhoá field in the Santos basin presalt offshore Brazil.

  Offshore
Digital Magazine
Look Inside
Cover
Current Issue

Oil & Gas Jobs

Search More Job Listings >>