Integrated fluids, solids control program improves drilling performance

Environmental targets met using inverted emulsion mud

Benjamin Paiuk, Oscar Daparo - M-I SwacoDaniel Aquino - ChevronTexaco Argentina

The environmental and economic impacts of using an inverted-emulsion drilling fluid were mitigated by managing mud constituents and treatment to reduce retention on cuttings. An Integrated Fluids Engineering (IFE) concept was employed to realize these and additional benefits. The IFE concept incorporated a team consisting of project engineer, IFE coordinator, mud engineer, solids control equipment technician, and technical support.

The operator’s main interest was to reduce liquid effluents to minimize the environmental impact of using an invert-emulsion drilling mud by reducing the volume of waste generated in each drilling stage. Lithology of the well required that drilling fluid be used to help manage formations with reactive clays, salt mantle-rocks and depleted sands. Otherwise, problems with lost circulation and wellbore instability were encountered in the area.

To achieve the goal, the drilling plan called for reducing both mud cutting retention (MCR) and cutting oil retention (COR), and for determining the optimal surfactant concentration to minimize the volume of mud lost on cuttings wetting.

Reduction of MCR and COR resulted in less volume of new mud required as compared to previous area wells. This also helped reduce the total volume of drilling fluid used.

Invert-emulsion storage tanks were used to store and reuse the mud in subsequent wells. That minimized preparation of fresh volumes of mud at the rig, which translated into saving in gas/oil consumption for mud preparation purposes.


This graph charts the depth in meters and the days required for drilling.
Click here to enlarge image

Because the mud was being reused, improvements in solids control equipment efficiency and in reduction of the waste volume due to MCR and COR were made to avoid buildup of low particle size distribution solids in the mud.

The mud formula used in the second stage of drilling contained the special surfactant in order to minimize MCR and COR. That reformulation solved the problem of cutting becoming stuck in the primary shale shakers screens and also in the mud cleaner. This problem had the effect of reducing the hardware working life. With the reformulation, an increase in shaker screen duration allowed the use of screens with greater mesh sizes, resulting in increased efficiency and reduced screen consumption.

By using the formula which modified the degree and type of drill solids wetting and optimized control of the solids, the objective of reducing the amount of mud retained on the cuttings exceeded the target established at the beginning of the project. This also translated into a reduction in the amount of fresh mud volume required. The modified system removed 62.9% of the solids from the primary shakers, an improvement from the 53% seen prior to the changes. The COR on solids discharge was reduced from 24% to 16%.

One major problem affecting drilling solids control was eliminated with the revised mud formula. Before, cuttings were sticking to the surface of the shale shaker screens, necessitating the use of low mesh screens - 40-60 in the primary shakers and 175 in the mud cleaner - to prevent excessive mud loss. After the reformulation, 140-175 mesh was run in the primary shakers and 205-325 in the mud cleaner. That produced an increased efficiency downstream in the decanter. In addition, the useful life of the screens was increased because the abrasive cleaning materials used before were not necessary. Before the change, shaker screens were lasting 80-100 hours or less. After the changeover, average screen duration at the primary shakers went to 320 hours and the useful life of the mud cleaner screens ranged from 350-550 operating hours.

Although there was an increased cost in additive consumption with the new formula, the total mud cost was reduced because less make-up oil was needed.

Chevron began as operator at El Trapial field in 1991 and has drilled around 700 wells to date. The typical drilling program calls for drilling to 120 m with a bentonitic water-base mud using a 12 1/4-in. bit and 9 5/8-in. casing. The second stage uses the invert emulsion mud with 8 1/2-8 3/4-in. bits and 7-in. casing. Drill time in this second stage runs 50-70 hours.

Related Articles

Origin confirms milestone in BassGas MLE project

Dec 16, 2014 Origin Energy Ltd., as operator of the BassGas joint venture offshore Australia, has confirmed that another milestone has been achieved in the BassGas Mid Life Enhancement project, with the lift of...

Alphastrut completes seven-figure North Sea contract

Dec 16, 2014

Aluminium support systems supplier Alphastrut has completed a seven-figure contract with BP which Alphastrut says has saved BP around 54 metric tons (60 tons) in weight.

SKF and Vantage combine to improve drillship fleet

Dec 16, 2014

SKF USA Inc. and Vantage Drilling Inc. have combined resources to improve the reliability of the Vantage Titanium Explorer and Platinum Explorer drillships.

HitecVision establishes new service group

Dec 16, 2014

HitecVision is establishing a new oil service group under the name Global Maritime Group by merging five companies in its portfolio.

Peak commissions new test facilities

Dec 16, 2014

Peak Well Systems has commissioned new ISO test facilities. one in Perth, Western Australia, and one in Aberdeen, Scotland, as part of its R&D.

Trending News

Oceanteam sells vessel stake to J. Ray McDermott Norway

Dec 19, 2014

Oceanteam Shipping ASA has completed the transfer of its 50% ownership stake in its jointly owned pipelay vessel CSV North Ocean 102 to J. Ray McDermott Norway.

Ennsub unveils new deepwater deployment systems

Dec 19, 2014

Ennsub has completed the design and manufacture of two workclass ROV deployment systems, which have been designed and manufactured for ROVOP and are due to be installed into a newbuild, Tier 1 pipelay vessel early in 2015.

‘Largest’ new gantry crane launches Nordic Trym vessel

Dec 19, 2014

The new shipyard facility of Honghua Offshore Oil & Gas Equipment Co. in Jiangsu, China, has launched its first ship, an IMT982 platform supply vessel named Nordic Trym. The vessel was launched in a unique way, using the yard’s new gantry crane. 

Offshore photo of the day

Schlumberger to support Mariner well operations

Dec 19, 2014

Statoil has contracted Schlumberger Oilfield UK to provide integrated drilling and well services on the Mariner field in the UK northern North Sea.

  Offshore
Digital Magazine
Look Inside
Cover
Current Issue

Oil & Gas Jobs

Search More Job Listings >>