South Pars Phase 13 drilling nears conclusion

Oct. 10, 2016
Drilling of wells from two platforms serving the South Pars Phase 13 project in the Persian Gulf should be complete in December, according to Masood Ziari, managing director of Petro Gohar Farasahel Kish Co.

Offshore staff

TEHRAN, Iran – Drilling of wells from two platforms serving the South Pars Phase 13 project in the Persian Gulf should be complete in December, according to Masood Ziari, managing director of Petro Gohar Farasahel Kish Co. (PGFK).

The company has been drilling 38 wells for this program since December 2014, he told news service Shana.

For the eight wells drilled from platform 13B, PGFK has employed the North Drilling Co. drilling rigSahar 1.