Songa Offshore SE provides Songa Dee SPS update

Oct. 20, 2014
Songa Offshore SE says that the scope of work for the Songa Dee special periodic survey has progressed according to plan, including the budget of 60 days and $90 million.

Offshore staff

LIMASSOL, CyprusSonga Offshore SE says that the scope of work for the Songa Dee special periodic survey (SPS) has progressed according to plan, including the budget of 60 days and $90 million. During its yard stay, the rig achieved its certification on hull and structure by DNV, and the BOP has been overhauled and lifted back on board. The commissioning of the BOP and the winch upgrades is in its final stages.   

During its yard stay, theSonga Dee has, however, experienced unexpected failure on one of its four main engines. Critical parts for the engine are being prepared for reinstallation. The rig is expected to leave Invergordon, Scotland, on Nov. 7, allowing it to be back on day rate a few days later. The costs related to the engine incident will be claimed against insurance and are not expected to impact the overall yard stay costs beyond the budget.

10/20/2014