Shell’s Olympus TLP in place, on target for 2014 startup

Offshore staff

HOUSTON – Shell’s Olympus tension leg platform (TLP) reached its destination at the deepwater Mars field and was safely secured in place at the end of July.

The 120,000-ton structure, said to be the largest TLP ever developed for the Gulf of Mexico, is expected to start production in 2014 at a rate of 100,000 boe/d. Olympus, the centerpiece of the Mars B development, will be moored in 3,000-ft (914-m) water depths in the Mississippi Canyon area, about one mile from the existing Mars platform, which has been producing since 1996.

During a June 5 tour of the TLP at the Kiewit Offshore Services yard in Ingleside, Texas, Shell officials said the Mars B project is be the first in the region to employ an additional floating production system in a producing deepwater field.

“This is the first time in the Gulf of Mexico that a company has built another host structure to go in an existing field,” rather than using subsea tiebacks to expand a field, said John Hollowell, Shell’s executive vice president for deepwater.

The new TLP hosts 24-slot drilling unit supplied by Nabors Industries and includes capacity for six subsea wells to gather production from the nearby West Boreas and South Diemos fields. Noble Corp.’s Noble Bully I has drilled the top sections of the 24 wells at Mars B, and is on location to drill the satellite wells at West Boreas and South Diemos.

The project is expected to extend the field life of Mars to at least 2050, Hollowell said. Shell has said the field could contain recoverable reserves of 1.1 Bboe. Shell operates the field with 71.5% interest; partner BP holds the remaining 28.5% interest.

When Olympus begins production, the focus of the existing Mars production platform will shift to the field’s shallower reservoirs and to water injection. Olympus, outfitted with 15,000 psi-rated trees furnished by FMC Technologies, will concentrate on high-pressure reservoirs that range in depth from 20,000-22,000 ft.

Shell will install a third platform at its West Delta 143 gathering hub to link production from Mars B with existing pipeline infrastructure.

Heerema’s Balder deepwater construction vessel will be used to install the TLP.

08/05/2013

Olympus TLP
(Photo courtesy Shell)

Related Articles

Petrobras starts-up FPSO Cidade de Ilhabela

Nov 21, 2014

Petrobras has started production through the FPSO Cidade de Ilhabela from the Sapinhoá field in the Santos basin presalt offshore Brazil.

Ophir finds deepwater gas in Tende offshore Tanzania

Nov 21, 2014

Ophir Energy says the drillship Deepsea Metro I has discovered gas while drilling the Tende-1 well in the East Pande block offshore Tanzania.

Technip to supply flexible pipe for Iracema North offshore Brazil

Nov 21, 2014

The Tupi BV consortium of Petrobras Netherland, BG, and Galphabe has contracted Technip to supply flexible pipe for the presalt Iracema North field in the Santos basin offshore Brazil.

Companies cooperate to deliver DNV GL-qualified deepwater lowering system

Nov 20, 2014 The cooperation of three companies jointly developing solutions for deepwater installation has led to the introduction of a new system capable of handling heavy loads at depths of well over 3 km (9...

CIMC Raffles delivers COSLProspector

Nov 20, 2014

CIMC Raffles has delivered in Yantai, Shandong, China, the fourth deepwater semisubmersible drilling rig built for COSL, the COSLProspector.

Trending News

Iran sanctions new wave of platform construction

Nov 26, 2014

New development projects are under way on two offshore Iranian fields in the Persian Gulf, according to news service Shana.

Gas reserves increase at Aphrodite offshore Cyprus

Nov 26, 2014

Delek Drilling says a review has raised estimated natural gas and condensate resources in the deepwater Aphrodite reservoir offshore Cyprus.

UK operators skeptical on ‘regime change,’ survey finds

Nov 26, 2014

Companies operating in the UK North Sea need to adapt to make the most of the sector’s potential, according to a new report from Deloitte.

Iran re-examines potential of Sepand gas field

Nov 26, 2014

Exploratory drilling has started at the Sepand gas field, 250 km (155 mi) from Kish Island in the Persian Gulf.

Topaz support vessel demand steady in Caspian, Middle East

Nov 26, 2014

Topaz Energy and Marine has added four new DP-2 platform supply vessels (PSVs) to its fleet this year: Topaz Seema, Topaz Xara, Topaz Faye, and Caspian Voyager

  Offshore
Digital Magazine
Look Inside
Cover
Current Issue

Oil & Gas Jobs

Search More Job Listings >>