FoundOcean completes GoM pipeline grout job for Saipem

Offshore staff

MARLOW, UK – FoundOcean has completed installation and grouting for a clamp repair on an 18-in. pipeline in the Gulf of Mexico under contract from Saipem America.

The seabed a water depth of 750 m (2,460 ft) was dredged at around the damaged area of the pipeline. An ROV maneuvered the two steel half-shells of the clamp into position and pre-tightened the bolts. FoundOcean then connected the hose to the inlet valve on the clamp and delivered the grout using its deepwater grouting umbilical system. Due to the extra load, a fabric formwork was installed under the clamp to provide more support.

In total 28 metric tons (30.86 tons) of cement was used: 4 metric tons (4.4 tons) for the clamp and 24 metric tons (26.46 tons) for the fabric formwork.

The pipeline damage resulted from an anchor drag during bad weather.

2/25/2013

Related Articles

VBMS to link Ravn to German North Sea platform

Jan 15, 2015

Wintershall has contracted VBMS for subsea works associated with the Ravn field development in the Danish North Sea.

Compact separation technology enhances subsea boosting

Jan 15, 2015 Implementation of subsea boosting over the last decades has included multi-phase pumps, some with separation and pumps combined. To further improve robustness, reduce risks, and reduce total capex,...

Woodside lines up deepwater well offshore South Korea

Jan 15, 2015

Woodside Petroleum says it plans to drill an exploratory well this fall on the deepwater Ulleung basin block 8/6-1N offshore eastern South Korea.

Statoil's subsea factory tackles the power source hurdle

Jan 15, 2015 Statoil's ambitious goal of launching a subsea factory in deeper and colder environments by 2020 is on track. By making incremental improvements and tapping into innovative technology from other in...

Seismic bids under review for deepwater block offshore Egypt

Jan 15, 2015

Petroceltic and partner Edison plan to acquire seismic data this year over their recently awarded North Thekah block in the deepwater Mediterranean Sea offshore Egypt. 

Trending News

BP has agreement in principle to settle governmental Macondo claims

Jul 2, 2015

BP has an agreement in principle to settle all federal and state claims arising from the Macondo oil spill in the Gulf of Mexico. 

Norwegian government realigns Johan Sverdrup field interests

Jul 2, 2015

The Norwegian Ministry of Petroleum and Energy has determined the various ownership interests in the Johan Sverdrup field in the central Norwegian North Sea.

South Pars Phase 1 platform capacity upgrade completed

Jul 2, 2015

Production capacity of Platform SPD1 serving Phase 1 of the South Pars gas field in the Persian Gulf has reached 1 bcm/d (35 bcf/d).

Noreco settles offshore Denmark liabilities

Jul 2, 2015

Norwegian Energy Co. (Noreco) has reached agreement with its joint venture partners in the Danish North Sea on its forfeited licenses and related abandonment liabilities.

COSCO Qidong extends delivery of semisubmersible accommodation rig to Axis Offshore

Jul 2, 2015

COSCO Qidong Offshore Co. Ltd. has agreed to extend the delivery of a harsh environment semisubmersible accommodation rig to Axis Offshore. 

  Offshore
Digital Magazine
Look Inside
Cover
Current Issue

Oil & Gas Jobs

Search More Job Listings >>