Riser overhaul completed at Norway platform

April 16, 2012
EMAS AMC has completed the first of several planned riser replacements for Statoil offshore Norway.

Offshore staff

STAVANGER, Norway – EMAS AMC has completed the first of several planned riser replacements for Statoil offshore Norway.

Engineering and planning started in January 2012, with offshore operations on the Snorre B platform implemented during March.

The scope for Snorre B in the North Sea and other floating platforms includes riser recovery and installation work. EMAS AMC has used itsAMC Connector vessel for the program.