Woodside chasing further gas for Pluto LNG

Offshore staff

PERTH, Australia – Woodside Energy (WPL:AU/WOPEY:US) says construction of the Pluto LNG foundation project in northwest Australia is in its final stages.

Offshore, the Pluto A platform was declared ready for start-up in November, and the subsea well commissioning campaign was completed in December.

Onshore, the jetty, storage and loading facilities are operational. Testing and independent running of major process equipment are progressing prior to start-up of the LNG train. Offshore gas was introduced into the processing plant last weekend, enabling final preparations for LNG production to begin.

Woodside continues to explore for fresh reserves for the project. The Ragnar-1 well in the offshore WA-430-P permit has reached target depth, intersecting gas over a gross interval of 190 m (623 ft).

The company next plans to drill an oil appraisal well in the Greater Laverda area before returning to the Ragnar Hub to drill Vucko-1 in WA-433-P, with further exploration wells to follow later in WA-389-P and WA-269-P.

Discussions continue with other resource owners regarding development of more trains at Pluto.

Last year Woodside completed the draft upstream environmental impact statement for the Browse basin LNG project and submitted the field development plan.

The company’s share of Browse contingent resources has increased from 1,187.7 MMboe to 1,439.2 MMboe. This is due to enhanced reservoir analysis at the Torosa and Calliance fields, seismic coverage from the Maxima survey, and reprocessing of existing data.

An ocean-bottom cable-deployed 3D seismic survey was acquired over the Torosa field, with interpretation due to be completed in the latter part of 2012.

The Browse Joint Venture has written to the Commonwealth Minister for Resources and Energy and the WA Minister for Mines and Petroleum requesting amendments to the Browse basin retention leases. The request includes a suggested deferral of final investment decision readiness from mid-2012 to the first half of 2013.

Finally, Woodside says the bridges that will connect the North Rankin A and North Rankin B platforms for the North Rankin development project have been completed in Indonesia.

In South Korea, fabrication of the NRB 23,000-metric ton (25,353-ton) topsides was finished in readiness for sail-away to the North West Shelf in early 2012. Topsides installation should take place before mid-year.

2/23/2012

Related Articles

Origin confirms milestone in BassGas MLE project

Dec 16, 2014 Origin Energy Ltd., as operator of the BassGas joint venture offshore Australia, has confirmed that another milestone has been achieved in the BassGas Mid Life Enhancement project, with the lift of...

Peak commissions new test facilities

Dec 16, 2014

Peak Well Systems has commissioned new ISO test facilities. one in Perth, Western Australia, and one in Aberdeen, Scotland, as part of its R&D.

Browse FLNG moves to FEED phase

Dec 16, 2014

Woodside Petroleum says the Browse Joint Venture has agreed to a revised schedule for front-end engineering and design (FEED) for the Browse FLNG development offshore northwest Australia.

Fairplayer to install Wheatstone subsea hardware offshore Western Australia

Dec 10, 2014

Technip Oceania has contracted Jumbo to install 13 subsea structures for Chevron’s Wheatstone project offshore Western Australia.

Statoil receives more blocks offshore New Zealand

Dec 9, 2014

Statoil has gained interests in four new exploration permits offshore New Zealand. 

Trending News

Husky Energy begins oil production at South White Rose extension

Jun 29, 2015

Husky Energy has commenced production from the South White Rose project in the Jeanne d’Arc basin offshore Newfoundland and Labrador.

ONGC hires gas hydrate offshore research vessel

Jun 29, 2015

The Oil and Natural Gas Commission of India has contracted the research vessel Chikyu from Japan Drilling Co. Ltd. to explore offshore India in the Krishna-Godavari and Mahanadi areas for gas hydrates.

First steel cut for Johan Sverdrup jacket, template

Jun 29, 2015

Construction work has started on facilities for the Statoil-operated Johan Sverdrup project in the central Norwegian North Sea.

TGS set to acquire Polarcus 3D, 2D seismic datasets

Jun 29, 2015

TGS has a letter of intent to acquire Polarcus’ entire multi-client library, with the exception of Australia, for $27.5 million.

Offshore US rig count increases

Jun 29, 2015

The US offshore rig count by Baker Hughes Inc. shows an increase of one rig over the prior week. 

  Offshore
Digital Magazine
Look Inside
Cover
Current Issue

Oil & Gas Jobs

Search More Job Listings >>