Baltic Sea pipeline preparations continue

Social Tools

Offshore staff

ZUG, Switzerland – Pre-commissioning has been completed on the first Nord Stream gas pipeline in the Baltic Sea, including pressure testing, cleaning, drying, and filling with nitrogen to eliminate any oxygen.

Earlier this week operations began to fill the first line with ‘buffer’ gas, and this will continue for around four weeks.

Before full service can start, the pipeline needs to be filled with gas to a certain level. This will be the final step in commissioning of the first line, allowing transportation of gas from Russian onshore fields to Europe.

After completion of preparatory works on both ends of the pipeline in Russia and Germany, gas should start flowing in October.

09/09/2011

Most Recent Content

Rosneft appoints president

Rosneft (MICEX:ROSN) has appointed Igor Sechin as president.

Island Offshore extends FMC contracts for North Sea LWI

FMC Technologies Inc. (NYSE:FTI) has signed two five-year contracts with Island Offshore Management AS to supply light well intervention (LWI) services for Statoil in the North Sea.

Record bids for latest UK license round

Britain has received a record number of applications in its latest offshore licensing round.

Cooper assigns Tunisia well operations to AGR

Cooper Energy has contracted AGR for drilling services offshore Tunisia.

Statoil takes LWI rigs on long-term charters

Statoil (OSE:STL;NYSE:STO) has awarded contracts totaling $1.56 billion for three new “Category A” light well intervention (LWI) vessels, two to Island Offshore Management and one to Eide Marine Services.

Offshore Magazine