Emerging markets to drive FPU construction over near term

April 9, 2015
Through the end of the decade, the largest markets for floating production systems are expected to remain Brazil, West Africa, and Southeast Asia. However, there are new areas of growth, particularly in East Africa and the Mexican portion of the Gulf of Mexico. The fastest growing segment is forecast to be gas processing units, namely FLNGs and FSRUs, which are expected to account for 25% of all floating production systems capital expenditures over the next five years.
Click image to EnlargeTotal capex of all FPS types by region ($, m) based on best case 2015-2019 forecast.
Charts courtesy Energy Maritime Associates Pte. Ltd.

David Boggs
Energy Maritime Associates Pte. Ltd.

Through the end of the decade, the largest markets for floating production systems are expected to remain in Brazil, West Africa, and Southeast Asia. However, there are new areas of growth, particularly in East Africa and the Mexican portion of the Gulf of Mexico.

The fastest growing segment is forecast to be gas processing units, namely FLNGs and FSRUs, which are expected to account for 25% of all floating production systems capex over the next five years.

However, oil processing units, especially FPSOs, will continue to be the dominant type of floating production systems worldwide. FPSOs are expected to account for 45% of the projected orders and 60% of the capex. Floating production systems are defined here to include FLNGs, FPSOs, FSOs, FSRUs, semisubmersibles, spars, and TLPs.

Five-year forecast

Between 105 to 188 floating production systems are expected to be built over the next five years with a total capital cost between $80.2 and $157.4 billion. The most likely forecast is 142 orders costing $118.5 billion. Units for Brazil and Africa will account for $48 billion of expenditure, followed by $30 billion in Australia and Southeast Asia, and over $25 billion in the Gulf of Mexico and Northern Europe. Significant growth is expected toward the end of the decade in Mexico as international companies enter the market.

Brazil and Africa should continue to attract the most capital investment over the next five years. Over $25 billion is the best case estimate for Brazil, driven by FPSOs for Petrobras. Africa is a close second with $23 billion of spending mainly on FPSO and FLNG projects. Approximately $15 billion will be spent in floater projects in Australia and Southeast Asia. Australia investments are dominated by large gas FLNGs and semis, while Southeast Asia has a mix of FPSOs, FLNGs, and FSOs. Projects for the US GoM and Europe are expected to cost around $10 billion, mostly on FPSOs in the North Sea. Units for the US GoM are spread amongst FPSOs, FLNG export terminals, spars, and production semis. A new growth area for the next five years is the Mexican side of the GoM, where $6.4 billion is expected to be spent on FPSOs and FSOs.

Brazil

FPSOs will account for almost all of the new units expected over the next five years in Brazil. Most, but not all, will be for Petrobras. The Brazilian state-owned company had planned to award at least 14 new floating production contracts over the next three years. However, this is unlikely to happen on schedule given the investigations and financial issues surrounding the company. There will be a delay in these awards, so we do not expect to see many contracts placed by Petrobras in 2015. However, the presalt fields have proven to be viable and additional FPSOs will be required for development. According to Petrobras and its partner BG, the break-even for many of these fields is $45/bbl.

Two non-Petrobras projects that could require FPSOs include Phase 2 of Queiroz Galvao's heavy-oil Atlanta development in block BS-4 and Karoon's Kangaroo discovery. In December 2014, Teekay was awarded a three + two year lease contract to redeploy the Petrojarl 1 FPSO for Phase 1 development of the Atlanta field. A larger FPSO with up to 80,000 b/d processing capacity could be required for the full field development. A redeployed FPSO could also be a viable solution for the Kangaroo field.

Click image to EnlargeProjects under appraisal, planning, and bidding/final design stage by region.

Africa

The vast majority of projects in Africa will continue to be located on the west coast, particularly off Angola and Nigeria. However, floating production units are also being used in new areas. Ghana received its first FPSO for Tullow's Jubilee field in 2010. Tullow selected Modec to provide another FPSO for the nearby TEN development, which is scheduled to begin production in 2016. In January 2015, Yinson was awarded a 15-year FPSO lease contract by Eni for its Sankofa/Gye Nyame development. Potential new projects in Ghana include an FPSO for the ultra-deepwater Tano Cape Three Points field and an FSRU as part of a natural gas-fired power plant development.

There are no floating production units in operation or on order for East Africa, but this is set to change with seven projects currently being planned. All of these are natural gas developments – three off Mozambique, three off Tanzania, and one off Kenya. BG is investigating use of multiple TLP units for its deepwater fields in Tanzania's block 1 (Mzia and Jodari) and block 4 (Pweza, Chewa, Ngisi). In Mozambique, a front-end engineering and design (FEED) competition is in progress for an FLNG unit to develop Eni's Coral gas fields in Area 4. In order to achieve first production by 2019, an award would be required in 2015. After Coral, Eni has plans for two additional FLNG units and an onshore plant to monetize Area 4's Mamba discoveries. An FSRU could be required as part of Kenya's Dongo Kundu power project.

Australia/New Zealand

Large FLNG units are expected to account for 75% of the capital cost for projects in Australia over the next five years. This includes Woodside's Browse development, which calls for three units. FEED is now planned to start by mid-2015 with final investment decision targeted for 2016. No new floating production systems are expected in New Zealand in the near future, although there has been some recent exploration activity.

Click image to EnlargeWater depth of current projects under appraisal, planning, and bidding/final design.

Southeast Asia

Despite the drop in oil prices, a number of projects are moving ahead in Southeast Asia. Hess recently awarded an FSO contract for its North Malay Basin project, which will process gas on a fixed platform and send condensate to the FSO. Kris Energy is progressing plans for its block A development offshore Cambodia, after taking over operatorship from Chevron in 2014. Projects are expected to be tendered later this year include a TLP and FPSO for Talisman's Red Emperor field off Vietnam and three projects off Indonesia – Premier Oil's Ande Ande Lumut FPSO, Husky's Madura MDA/MBH Production Barge, and possibly the third tender for Chevron's Gendalo/Genham production barges.

Over the next five years, more than $5 billion in capex is expected for various FLNG projects in Southeast Asia, particularly the Abadi field development in Indonesia. A 2.5 mtpa FLNG facility is planned for Phase 1, which is completing FEED. Another facility would be required for Phase 2, which is scheduled to enter FEED this year.

US GoM

A mix of FPSOs, production semisubmersibles, spars, and FLNG units will account for $10 billion of investment. At least eight FLNG projects have been proposed, but most are not likely to move forward in the near future. SBM Offshore is scheduled to deliver an FPSO for Shell's Stones development in 2016. This will be the second FPSO on the US side of the Gulf of Mexico and the deepest floating production unit – moored in 2,900 m (9,514 ft) of water. Another FPSO could be required by the end of the decade for BP's Kaskida field, located in 1,800 m (5,905 ft) of water in block KC 292.

However, there has been a recent trend toward tiebacks to existing facilities in the US Gulf, including Noble's Big Bend and Dantzler fields, ExxonMobil's Hadrian gas field, and Chevron's deepwater Buckskin/Moccasin de-velopment. Tieback to an existing asset can provide a faster and less expensive alternative to a stand-alone facility, depending on the distance, capacity, and charges of the host facility.

Click image to EnlargeWhat regions or countries will present the largest growth opportunities over the next five-10 years?

Mexican GoM

Following the reforms in Mexico, there will certainly be an increase in the number of floating production units from the one FSO and one FPSO currently in operation, in addition to a few small well testing units. However, this will take time. After the new leases are granted, it will take at least two to three years before contracts are placed for these new facilities. PEMEX began discussions for two FPSOs in 2013, but has yet to place the contract. These would be leased units – a very large unit for the Ayatsil/Tekel field and a dynamically positioned unit to perform extended well tests in various locations.

Northern Europe

Twenty-six projects are in the planning phase in Northern Europe, predominantly the UK and Norway. FPSOs are the likely solution for 80% of developments, with 20% using FSOs and production semisubmersibles. Only two new floating production projects were sanctioned in 2014, down from three in 2013 and four in 2011 and 2012. This is largely due to increasing costs, which have forced review for new developments including Rosebank in the UK and Johan Castberg in Norway.

There has been much discussion of production from the Arctic. While there are interesting prospects in areas farther north of current facilities, we do not expect to see any arctic floating production units before the end of the decade.

Planning pipeline

Energy Maritime Associates (EMA) has identified 235 projects that potentially could require a floating production system. These projects are declared discoveries or planned developments where a floating production or storage system could be a development option. Since last year, there have been declines in the number of viable projects off Africa, Brazil, and Southwest Asia. These are predominantly deepwater fields with insufficient recoverable resources. However, these declines have been offset by new potential projects in the North Sea, Gulf of Mexico, and Southeast Asia.

By level of development

Of these 235 potential projects, 29% are in the bidding/final design stage, with Africa and Southeast Asia the most active regions. Final investment decisions and contract awards for these projects are possible in the next 12-24 months. 46% of projects are in the planning stage. A number of these projects from northern Europe, Gulf of Mexico, and Brazil have yet to move to the bidding/final design stage due to technical complexity and regulatory environment. The final 25% are in the appraisal stage, predominantly deepwater discoveries in Brazil and Africa.

By water depth

Before 2000, almost all floating production units were located in less than 1,000 m (3,280 ft) of water. Since 2010, over half of new units are located in more than 1,000 m, including 30% in more than 1,500 m (4,921 ft). For projects in the planning pipeline, 59 projects (25%) are in ultra-deepwater and 38 projects (16%) are in water depths of 1,000 to 1,500 m. The remaining 138 projects (61%) are in less than 1,000 m. Brazil and Africa account for the vast majority of deepwater projects – 63% of projects located in more than 1,000 m waters are in these two areas.

Many of the smaller deepwater developments will struggle to be economically viable in the current environment. However, the larger deepwater fields, such as Brazil's presalt fields should remain attractive. BG and Petrobras reported that their presalt developments had a break-even of $45/bbl.

Industry sentiment

The results of EMA's 2015 Floating Production Industry Survey largely fulfilled the firm's expectations, with a few exceptions. In terms of regions with the largest growth opportunities, most respondents agreed that Brazil, West Africa, and Southeast Asia would be the dominant areas. Very few were excited about the prospects for Australia, while EMA believes that there will be a few, extremely large FLNG projects there in the next five years. Perhaps the lack of enthusiasm is explained by the limited number of projects, despite the very large capex.